Handover and operation of a lift after installation
An installed lift does not go into operation by itself: first comes conformity assessment under TR CU 011/2011, then notification and registration with Rostekhnadzor (the Russian industrial safety authority), then operation under the rules approved by Government Decree No. 1744. Below is the procedure and the documents at each step.
Step 1. Conformity assessment of the installed lift
Before putting into operation, conformity of the installed lift with TR CU 011/2011 is confirmed by declaration under scheme 4d (article 6). The procedure:
- the applicant prepares its own evidence and applies to an accredited testing laboratory;
- the evidence — a report on checking the operation of the lift after installation, the lift passport, the installation drawing of the installed lift and the design documentation;
- the laboratory carries out a full technical examination and issues a certificate;
- if the results are positive, the applicant adopts and registers the declaration of conformity.
How exactly the examination is carried out — tests, measurements and checks, electrical measurements, requirements for measuring instruments and for recording results — is set by GOST 34582-2019. Declaration by the installation company is described separately in GOST R 71557-2024.
Step 2. Putting into operation and registration
The building owner decides to put the lift into operation and notifies the authorised body — Rostekhnadzor. The notification is filed within 10 days of the decision, on paper or as an electronic document with an enhanced qualified signature, or via the Gosuslugi public services portal. The authority enters the facility and the owner into the register and issues a registration number: within 5 working days, or 3 working days when filed via Gosuslugi. The registration number is entered in the lift passport.
By this point the owner must have: the registered declaration of conformity (and the certificate for the equipment itself), the manufacturer's passport and operating manual, a contract with a specialised installation company, certificates per GOST 22845-2018 and an owner's civil liability insurance policy.
Step 3. Operation
- Technical examination at least once every 12 months during the designated service life (TR CU 011/2011, art. 6, cl. 4). Methods and rules of checks during operation — GOST 34583-2019.
- Organisation of operation, inspections, emergency maintenance, remote monitoring, appointment of responsible persons and keeping of logs (including electronic ones with a qualified signature) — Government Decree No. 1744 of 20.10.2023, in force from 01.09.2024, and GOST R 55964-2022.
- Lifts in apartment buildings will be maintained only by companies on the Rostekhnadzor register — Federal Law No. 564-FZ of 29.12.2025. The start date was postponed from 1 September 2026 to 1 September 2027 — Federal Law No. 131-FZ of 02.05.2026.
- After the designated service life expires, conformity is assessed by a survey: the condition of the equipment is determined, defects are identified, insulation is tested, and a report with recommendations on modernisation or replacement is issued (TR CU 011/2011, art. 6, cl. 5). Operation of lifts past their designated service life is extended until 15.02.2030 — EEC Decision No. 112.
- The installation company's warranty on installation and commissioning is no less than the period established by law (GOST 22845-2018, section 10); fix the specific period in the contract.