Preparing the building part for lift installation
Lift installation starts not with the equipment but with acceptance of the building part. The procedure and tolerances are set by GOST 22845-2018 “Lifts. Electric lifts. Installation, starting-up and adjustment works. Rules of organisation and performance of works, performance control and requirements to results of works” (in force from 1 December 2018, replacing GOST 22845-85): under it the shaft is handed over to the installation company with a certificate, and under it the installers are entitled to refuse the shaft.
When installation may start
Installation starts when the conditions of cl. 4.10 are met:
- the building part is ready — building, finishing and welding work in the shaft and in the rooms for lift equipment is complete;
- certificates for the lift and its safety components and the full set of technical documentation (cl. 5.3.4) are available;
- storage areas for the equipment are ready; on a new building it is stored within reach of the crane that will lift it into the shaft (cl. 4.7);
- scaffolding in the shaft (if needed) and guards for the door openings are ready;
- distribution boards are installed for connecting the lift power circuit, the welding set, power tools and the temporary lighting of the shaft, machine room and pulley room;
- a room for a workshop, or a place for a mobile workshop connected to the power supply, is ready.
Scaffolding over the full height of the shaft at 1.8–3.0 m intervals is installed where the work execution plan (PPR) provides for it: the standard also allows installation without scaffolding, using the rigging and lifting gear specified by the lift manufacturer (cl. 4.9). Readiness is checked no later than 10 days before installation starts (cl. 5.1.1).
What is checked before installation
- the as-built drawing of the shaft (attached to the survey certificate, appendix A) — against the lift installation design and the requirements of section 6;
- the finished floor level mark on the inside wall of the landing door opening, for a through car — at both openings;
- scaffolding and door opening guards — where the PPR provides for them;
- temporary shaft lighting of no more than 50 V with at least 50 lx at the workplace; lamps above the scaffolding, where they do not hinder installation (cl. 5.2.2, 6.11).
Defects are recorded in the survey certificate (appendix A); once they are remedied, the certificate of readiness of the building part for installation (appendix B, mandatory form) and the certificate of readiness of the scaffolding and door opening guards (appendix C) are drawn up (cl. 5.2.3, 5.2.4).
Tolerances for accepting the shaft
Deviations of the actual dimensions of the building part from nominal must not exceed the values in the lift installation design, including (cl. 6.1):
| What is checked | Tolerance | Clause |
|---|---|---|
| Perpendicularity of the inner surface of shaft walls to the horizontal plane (at pit floor level) | max. 30 mm | 6.1 |
| Internal plan dimensions of the shaft against the design | max. +30 mm | 6.1 |
| Difference between shaft diagonals in plan | max. 25 mm | 6.1 |
| Symmetry of embedded plates for car and counterweight rail brackets | max. 10 mm | 6.1 |
| Height level of embedded plates for guide rails | max. 80 mm | 6.1 |
| Position of other embedded parts for lift equipment | max. 10 mm | 6.1 |
| Exposed surface of embedded parts relative to the reference surface | 3 mm in and out | 6.1 |
| The same for surface-mounted parts | 3 mm in, 10 mm out | 6.1 |
| Parallelism of the exposed surface of embedded parts | max. 3 mm | 6.1 |
| Holes in the floor of the machine and pulley rooms | max. +10 mm | 6.1 |
| Distance from the buffer bearing surface to the finished floor of the lowest landing | max. 10 mm | 6.1 |
| Symmetry of the landing door opening axis | max. 10 mm | 6.1 |
| Temporary installation openings when landings are more than 6 m apart | 800 × 1,500 mm at intervals of max. 6 m | 6.3 |
| Separator beams between lifts in a common shaft | max. 100 mm wide, max. 20 mm out of one vertical plane over the full height; mesh of 1.2 mm wire with openings of max. 20 mm | 6.4 |
| Height level of separator beams | max. 80 mm | 6.5 |
| Parallelism of separator beams to the horizontal plane | max. 1 mm per 1 m of length | 6.6 |
| Gap between the building and a steel-frame shaft inside the building | min. 10 mm | 6.7 |
Exposed surfaces of embedded parts and steel beams are cleaned of paint and concrete (cl. 6.2). Shafts made of precast concrete units — to GOST 17538 (cl. 6.10).
Pit, rooms, guards, power supply
- The shaft pit is protected against groundwater and wastewater (cl. 6.9): waterproofing and drainage are done before installation.
- Machine and pulley room dimensions follow the lift installation design; a lockable door is installed before the equipment in these rooms is installed (cl. 6.8).
- All door openings and temporary installation openings are guarded to a height of at least 1.1 m: a toe board of at least 100 mm at the bottom and a mid-rail at 500–550 mm; the guard withstands 900 N applied at any point in any direction (cl. 6.12).
- Scaffolding (where the PPR provides for it): gap from the wall to the edge of the deck of max. 300 mm, with fixed ladders or ramps for access (cl. 6.13).
- Commissioning is carried out only with a permanent power supply and protective earthing; the voltage drop at the terminals of the input device when the lift starts is no more than 8% (cl. 8.2).
Sequence of work and certificates
| Stage | Document | Clause |
|---|---|---|
| Survey of the building part, defects | certificate per appendix A (with the as-built drawing of the shaft) | 5.2.3 |
| Readiness of the building part for installation | certificate per appendix B — mandatory form | 5.2.4 |
| Readiness of scaffolding and door opening guards | certificate per appendix C | 5.2.4 |
| Acceptance of equipment against the packing list and the manufacturer's packing sheets | certificate per appendix D | 5.3.3 |
| Handover of the lift for building and finishing works (where provided for by the design) | certificate per appendix E | 7.12 |
| Handover of the lift for commissioning — recommended after finishing works | certificate per appendix F | 8.1 |
Appendices A–F here correspond to appendices А, Б, В, Г, Д, Е of the Russian original.
Handed over with the lift: the passport, the circuit diagram with the list of elements, a copy of the lift certificate, copies of certificates for the safety components and, where needed, for fire doors, the operating manual, the installation instructions and the installation drawing (cl. 5.3.4). Putting the lift into operation is a separate stage with its own documents: handover after installation.
Installation warranty
The company that carried out installation and commissioning gives a warranty on this work of no less than the period established by law (section 10). Fix the specific period in the contract.
Related
- Handover after installation: tests, declaration, registration
- GOST 22845-2018 in the register of standards
- Pit: depth and requirements
- Shaft headroom
- Shaft sizes by rated load