Preparing the building part for lift installation

Lift installation starts not with the equipment but with acceptance of the building part. The procedure and tolerances are set by GOST 22845-2018 “Lifts. Electric lifts. Installation, starting-up and adjustment works. Rules of organisation and performance of works, performance control and requirements to results of works” (in force from 1 December 2018, replacing GOST 22845-85): under it the shaft is handed over to the installation company with a certificate, and under it the installers are entitled to refuse the shaft.

When installation may start

Installation starts when the conditions of cl. 4.10 are met:

Scaffolding over the full height of the shaft at 1.8–3.0 m intervals is installed where the work execution plan (PPR) provides for it: the standard also allows installation without scaffolding, using the rigging and lifting gear specified by the lift manufacturer (cl. 4.9). Readiness is checked no later than 10 days before installation starts (cl. 5.1.1).

What is checked before installation

Defects are recorded in the survey certificate (appendix A); once they are remedied, the certificate of readiness of the building part for installation (appendix B, mandatory form) and the certificate of readiness of the scaffolding and door opening guards (appendix C) are drawn up (cl. 5.2.3, 5.2.4).

Tolerances for accepting the shaft

Deviations of the actual dimensions of the building part from nominal must not exceed the values in the lift installation design, including (cl. 6.1):

What is checkedToleranceClause
Perpendicularity of the inner surface of shaft walls to the horizontal plane (at pit floor level)max. 30 mm6.1
Internal plan dimensions of the shaft against the designmax. +30 mm6.1
Difference between shaft diagonals in planmax. 25 mm6.1
Symmetry of embedded plates for car and counterweight rail bracketsmax. 10 mm6.1
Height level of embedded plates for guide railsmax. 80 mm6.1
Position of other embedded parts for lift equipmentmax. 10 mm6.1
Exposed surface of embedded parts relative to the reference surface3 mm in and out6.1
The same for surface-mounted parts3 mm in, 10 mm out6.1
Parallelism of the exposed surface of embedded partsmax. 3 mm6.1
Holes in the floor of the machine and pulley roomsmax. +10 mm6.1
Distance from the buffer bearing surface to the finished floor of the lowest landingmax. 10 mm6.1
Symmetry of the landing door opening axismax. 10 mm6.1
Temporary installation openings when landings are more than 6 m apart800 × 1,500 mm at intervals of max. 6 m6.3
Separator beams between lifts in a common shaftmax. 100 mm wide, max. 20 mm out of one vertical plane over the full height; mesh of 1.2 mm wire with openings of max. 20 mm6.4
Height level of separator beamsmax. 80 mm6.5
Parallelism of separator beams to the horizontal planemax. 1 mm per 1 m of length6.6
Gap between the building and a steel-frame shaft inside the buildingmin. 10 mm6.7

Exposed surfaces of embedded parts and steel beams are cleaned of paint and concrete (cl. 6.2). Shafts made of precast concrete units — to GOST 17538 (cl. 6.10).

Pit, rooms, guards, power supply

Sequence of work and certificates

StageDocumentClause
Survey of the building part, defectscertificate per appendix A (with the as-built drawing of the shaft)5.2.3
Readiness of the building part for installationcertificate per appendix B — mandatory form5.2.4
Readiness of scaffolding and door opening guardscertificate per appendix C5.2.4
Acceptance of equipment against the packing list and the manufacturer's packing sheetscertificate per appendix D5.3.3
Handover of the lift for building and finishing works (where provided for by the design)certificate per appendix E7.12
Handover of the lift for commissioning — recommended after finishing workscertificate per appendix F8.1

Appendices A–F here correspond to appendices А, Б, В, Г, Д, Е of the Russian original.

Handed over with the lift: the passport, the circuit diagram with the list of elements, a copy of the lift certificate, copies of certificates for the safety components and, where needed, for fire doors, the operating manual, the installation instructions and the installation drawing (cl. 5.3.4). Putting the lift into operation is a separate stage with its own documents: handover after installation.

Installation warranty

The company that carried out installation and commissioning gives a warranty on this work of no less than the period established by law (section 10). Fix the specific period in the contract.

GOST 22845-2018 replaced GOST 22845-85: the numerical shaft tolerances are unchanged, but temporary lighting is now up to 50 V (was 42 V), scaffolding is required only where the PPR provides for it, the requirements for opening guards are more detailed, and the standard no longer sets specific warranty periods (the old one had 6 months and 2 years for residential buildings). Safety requirements for the lift itself are set by TR CU 011/2011 and GOST 33984.1-2023, dimensions and embedded parts by the manufacturer's installation drawing.